PRINCE2 Agile Foundation Certification Exam is a globally recognized certification that focuses on the principles of PRINCE2 and Agile methodologies. It is designed to provide individuals with the knowledge and skills required to effectively manage projects in an agile environment. PRINCE2 Agile Foundation certification is suitable for professionals who are looking to improve their project management skills and expand their knowledge of agile methodologies.
NEW QUESTION # 26
What BEST defines embryonic customer requirements?
- A. Technical stories
- B. 'Fine-grained' user stories
- C. Sub-products
- D. Epics
Answer: D
NEW QUESTION # 27
Which is a purpose of the 'managing product delivery' process?
- A. To agree on what is required for accepting, executing and delivering project work.
- B. To plan the delivery of the products before committing to significant expenditure
- C. To establish and deliver the project communications to the wider organization
- D. To delegate day-to-day management of the project to the project manager
Answer: A
NEW QUESTION # 28
What term is used to describe boards that display what work needs to be completed for people working on a project?
- A. Work in progress limit
- B. Highlight report
- C. Glad! Sad! Mad!
- D. Information radiator
Answer: B
NEW QUESTION # 29
Which statement about the 'directing a project' process is CORRECT?
- A. The project board should attend regular project progress meetings
- B. A project board member should fulfill the product owner role within a delivery team
- C. The project board should increase the stage-level time tolerance
- D. The project board should make decisions based on the Agilometer risks
Answer: B
NEW QUESTION # 30
Why are team working agreement produced?
- A. To make the team rules visible to the project manager for monitoring purposes
- B. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
- C. To create structure so that the team manager can assess individual performance
- D. To ensure that the delivery team members comply with company policy
Answer: B
Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true
NEW QUESTION # 31
When creating the project product description, how should the purpose of the project product be defined?
- A. As an outcome
- B. As an opportunity
- C. As a vision
- D. As a goal
Answer: A
NEW QUESTION # 32
Which statement about quality tolerances for a product is CORRECT in an agile context?
- A. Setting quality tolerance relies on prioritising quality criteria
- B. All quality criteria tolerance must be fixed
- C. Quality tolerances should be the same for all quality criteria
- D. All quality criteria should have zero tolerance
Answer: A
NEW QUESTION # 33
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It is achieved by using the same team members
- B. It is achieved by allowing enough time for testing
- C. It gives confidence on the progress of the project
- D. It delivers the early realization of benefits
Answer: D
Explanation:
Reference:
%20level%20is%20met
NEW QUESTION # 34
Which is a key objective of running a workshop?
- A. To encourage collaboration and create the defined outputs from the event
- B. To make daily progress visible to the delivery team and key stakeholders
- C. To communicate decisions to the wider stakeholder community
- D. To make day-to-day decisions on behalf of the delivery team within a sprint
Answer: A
NEW QUESTION # 35
What needs to happen when new detailed requirements are added to a timebox?
- A. More people should be added to the delivery team
- B. Formal change control should be applied
- C. The delivery milestones should be reviewed and re-planned
- D. Requirements of a similar level of effort should be removed
Answer: D
NEW QUESTION # 36
Which TWO project board responsibilities are specifically assigned to the senior user?
1) Demonstrating the achievement of benefits.
2) Specifying the needs of those impacted by the outputs.
3) Balancing business, user and supplier demands.
4) Ensuring that the project delivers value for money.
- A. 2 and 3
- B. 1 and 4
- C. 3 and 4
- D. 1 and 2
Answer: D
NEW QUESTION # 37
Which statement about an epic is CORRECT?
- A. It can be broken down into user stories
- B. Its purpose is to document technical requirements
- C. It contains sufficient granularity to allow work to start
- D. It should appear at the top of a product backlog
Answer: A
NEW QUESTION # 38
In Scrum, what answers the question 'what can be done this sprint?'
- A. Sprint planning
- B. Sprint review
- C. Daily scrum
- D. Increment
Answer: C
NEW QUESTION # 39
Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?
- A. Because it is designed to manage projects, delivering products in timeboxes
- B. Because it explains how a small company can grow using traditional technologies
- C. Because it enables agile to be used in challenging and uncertain situations
- D. Because running a project and setting up a new business are the same
Answer: C
NEW QUESTION # 40
Which is a purpose of the 'controlling stage' process?
- A. To establish whether the project is complete
- B. To execute and deliver the project product
- C. To draft the plan for the next stage's work
- D. To report stage progress to the project board
Answer: D
Explanation:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control
NEW QUESTION # 41
Which is often used during a retrospective to capture lessons?
- A. A burn chart
- B. A Kanban board
- C. A Glad! Sad! Mad! board
- D. A Gantt chart
Answer: C
NEW QUESTION # 42
What does velocity typically measure?
- A. The rate of progress the team is making
- B. Work packages completed by the team
- C. The speed that a minimum viable product is created
- D. The number of timeboxes completed
Answer: A
NEW QUESTION # 43
Which is an advantage of using the PRINCE2 Agile behavior 'collaboration'?
- A. It ensures that there are no surprises
- B. It uses experimentation to expand requirements
- C. It allows people to provide cover for one another
- D. It uses learning to help improve products
Answer: D
NEW QUESTION # 44
What should be decided when configuring PRINCE2 effectively?
- A. Where to put the emphasis and where to add guidance
- B. What to remove and where to add guidance
- C. Which areas are not enabled to work with agile
- D. What to significantly change to create the right blend
Answer: D
NEW QUESTION # 45
What is the MOST LIKELY benefit from frequent releases into operational use?
- A. Feedback is obtained from real customers
- B. The risks associated with agile ways of working are assessed
- C. The need for configuration management is reduced
- D. The need for customer involvement is increased
Answer: A
NEW QUESTION # 46
......
PRINCE2 Agile Foundation Exam is an excellent opportunity for professionals to enhance their project management skills and gain recognition for their knowledge and expertise in the field. PRINCE2 Agile Foundation certification is globally recognized and is highly regarded by employers and organizations worldwide. PRINCE2 Agile Foundation certification is also an excellent stepping stone for professionals who wish to pursue higher-level certifications such as the PRINCE2 Agile Practitioner or the PRINCE2 Practitioner certification.
PRINCE2-Agile-Foundation Study Guide Realistic Verified Dumps: https://www.trainingquiz.com/PRINCE2-Agile-Foundation-practice-quiz.html
Self-Study Guide for Becoming an PRINCE2 Agile Foundation Expert: https://drive.google.com/open?id=14mhhjNZa2kC8HUz4fdyj7V6V-TABw3Tj