CAP exam is part of the new Certified Authorization Professional (CAP) certification. This exam measures your ability and skills related to information security practitioner. Candidates will need to show they have technical skills to advocates for security risk management in pursuit of information system authorization to support an organization's mission and operations in accordance with legal and regulatory requirements.
NEW QUESTION # 23
Which of the following NIST C&A documents is the guideline for identifying an information system as a National Security System?
- A. NIST SP 800-53
- B. NIST SP 800-59
- C. NIST SP 800-37
- D. NIST SP 800-53A
Answer: B
Explanation:
Section: Volume D
Explanation/Reference:
NEW QUESTION # 24
Which of the following approaches can be used to build a security program?
Each correct answer represents a complete solution. Choose all that apply.
- A. Top-Down Approach
- B. Left-Up Approach
- C. Bottom-Up Approach
- D. Right-Up Approach
Answer: A,C
Explanation:
Section: Volume B
NEW QUESTION # 25
Frank is the project manager of the NHH Project. He is working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team.
What document is Frank and the NHH Project team creating in this scenario?
- A. Resource management plan
- B. Risk management plan
- C. Project plan
- D. Project management plan
Answer: B
Explanation:
Section: Volume A
NEW QUESTION # 26
ISO 17799 has two parts. The first part is an implementation guide with guidelines on how to build a comprehensive information security infrastructure and the second part is an auditing guide based on requirements that must be met for an organization to be deemed compliant with ISO 17799. What are the ISO
17799 domains?
Each correct answer represents a complete solution. Choose all that apply.
- A. System architecture management
- B. Personnel security
- C. System development and maintenance
- D. Business continuity management
- E. Information security policy for the organization
Answer: B,C,D,E
Explanation:
Section: Volume B
NEW QUESTION # 27
In 2003, NIST developed a new Certification & Accreditation (C&A) guideline known as FIPS 199.
What levels of potential impact are defined by FIPS 199?
Each correct answer represents a complete solution. Choose all that apply.
- A. Low
- B. Medium
- C. High
- D. Moderate
Answer: A,B,C
Explanation:
Section: Volume C
NEW QUESTION # 28
After purchasing an item on an e-commerce website, a user can view his order details by visiting the URL:
https://example.com/order_id=53870
A security researcher pointed out that by manipulating the order_id value in the URL, a user can view arbitrary orders and sensitive information associated with that order_id.
Which of the following is correct?
- A. The root cause of the problem is a lack of input validation and by implementing a strong whitelisting, the problem can be solved
- B. None of the above
- C. The problem can be solved by implementing a Web Application Firewall (WAF)
- D. The root cause of the problem is a weak authorization (Session Management) and by validating a user's privileges, the issue can be fixed
Answer: D
Explanation:
The scenario describes an e-commerce website where a user can view order details by manipulating the order_id parameter in the URL (e.g., https://example.com/order_id=53870). A security researcher found that changing the order_id allows access to arbitrary orders and sensitive data, indicating an authorization issue.
This is not a simple input validation problem (e.g., SQL injection or path traversal), as the input (order_id) is processed, but the system fails to enforce proper access controls. This is a classic case ofInsecure Direct Object References (IDOR), where an attacker can access resources by guessing or manipulating identifiers without proper authorization checks. The root cause is a weak authorization mechanism, likely tied to poor session management orprivilege validation, allowing unauthorized users to view others' data.
* Option A ("The root cause of the problem is a lack of input validation..."): Incorrect, as the issue is not about invalid input (e.g., malicious code) but about unauthorized access to valid data. Whitelisting might help sanitize input, but it doesn't address authorization.
* Option B ("The root cause of the problem is a weak authorization (Session Management)..."):
Correct, as the problem stems from inadequate authorization checks. Validating user privileges (e.g., ensuring the user can only access their own orders) or improving session management (e.g., tying orders to user sessions) can fix this IDOR vulnerability.
* Option C ("The problem can be solved by implementing a Web Application Firewall (WAF)"):
Incorrect as a standalone solution, as WAFs mitigate certain attacks (e.g., SQLi, XSS) but are not a substitute for fixing authorization logic. A WAF might detect patterns but won't enforce proper access control.
* Option D ("None of the above"): Incorrect, as Option B accurately identifies the root cause and solution.
The correct answer is B, aligning with the CAP syllabus under "Authorization and Access Control" and
"OWASP Top 10 (A04:2021 - Insecure Design)."References: SecOps Group CAP Documents - "Session Management," "Insecure Direct Object References (IDOR)," and "OWASP Top 10" sections.
NEW QUESTION # 29
Which of the following statements best describes the difference between the role of a data owner and the role of a data custodian?
- A. The custodian makes the initialinformation classification assignments, and the operations manager implements the scheme.
- B. The data owner implements the information classification scheme after the initial assignment by the custodian.
- C. The datacustodian implements the information classification scheme after the initial assignment by the data owner.
- D. The custodian implements the information classification scheme after the initial assignment by the operations manager.
Answer: C
NEW QUESTION # 30
Which of the following individuals is responsible for preparing and submitting security status reports to the organizations?
- A. Chief Information Officer
- B. Common Control Provider
- C. Authorizing Official
- D. Senior Agency Information Security Officer
Answer: B
Explanation:
Section: Volume D
NEW QUESTION # 31
Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?
- A. Project costs will increase.
- B. The amount of hours a resource can be used will diminish.
- C. The projectwill take longer to complete, but risks will diminish.
- D. Project risks will increase.
Answer: A
NEW QUESTION # 32
Which of the following processes has the goal to ensure that any change does not lead to reduced or compromised security?
- A. Change control management
- B. Configuration management
- C. Risk management
- D. Security management
Answer: A
Explanation:
Section: Volume D
NEW QUESTION # 33
Which of the following persons is responsible for testing and verifying whether the security policy is properly implemented, and the derived security solutions are adequate or not?
- A. User
- B. Data custodian
- C. Data owner
- D. Auditor
Answer: D
NEW QUESTION # 34
Which of the following individuals is responsible for the final accreditation decision?
- A. Information System Owner
- B. Risk Executive
- C. Certification Agent
- D. User Representative
Answer: A
Explanation:
Section: Volume D
NEW QUESTION # 35
Fred is the project manager of the PKL project. He is working with his project team to complete the quantitative risk analysis process as a part of risk management planning. Fred understands that once the quantitative risk analysis process is complete, the process will need to be completed again in at least two other times in the project. When will the quantitative risk analysis process need to be repeated?
- A. Quantitative risk analysis process will be completed again after the risk response planning and as a part of monitoring and controlling.
- B. Quantitative risk analysisprocess will be completed again after the plan risk response planning and as part of procurement.
- C. Quantitativerisk analysis process will be completed again after new risks are identified and as part of monitoring and controlling.
- D. Quantitative risk analysis process will be completed again after the cost managementplanning and as a part of monitoring and controlling.
Answer: A
NEW QUESTION # 36
Which of the following C&A professionals plays the role of an advisor?
- A. Chief Information Officer (CIO)
- B. Authorizing Official
- C. Information System Security Engineer (ISSE)
- D. Information Owner
Answer: C
NEW QUESTION # 37
The National Information Assurance Certification and Accreditation Process (NIACAP) is the minimum standard process for the certification and accreditation of computer and telecommunications systems that handle U.S. national security information. Which of the following participants are required in a NIACAP security assessment?
Each correct answer represents a part of the solution. Choose all that apply.
- A. IS program manager
- B. User representative
- C. Information Assurance Manager
- D. Designated Approving Authority
- E. Certification agent
Answer: A,B,D,E
Explanation:
Section: Volume C
NEW QUESTION # 38
The DNS entries forwww.ironman.comandwww.hulk.comboth point to the same IP address i.e., 1.3.3.7. How does the web server know which web application is being requested by the end user's browser?
- A. The web server inspects the cookies sent by the client.
- B. The web server uses a reverse DNS lookup of the client's IP address.
- C. The web server inspects the client's SSL certificate.
- D. The web server inspects the HTTP "Host" header sent by the client.
Answer: D
Explanation:
When multiple domain names (e.g.,www.ironman.comandwww.hulk.com) resolve to the same IP address (e.
g., 1.3.3.7), a web server hosting multiple applications on that IP must determine which application to serve.
This is achieved using theHTTP "Host" header, which is part of the HTTP/1.1 protocol. The client (browser) includes the requested domain (e.g., Host: www.ironman.com) in the request, allowing the server to route the request to the appropriate virtual host or application configured for that domain. This is a standard practice in virtual hosting.
* Option A ("The web server inspects the HTTP 'Host' header sent by the client"): Correct, as the Host header enables the server to distinguish between applications on the same IP.
* Option B ("The web server inspects the cookies sent by the client"): Incorrect, as cookies are used for session management or personalization, not for identifying the requested application.
* Option C ("The web server inspects the client's SSL certificate"): Incorrect, as SSL certificates are used for encryption and authentication, not for application routing (though they may include the domain name for validation).
* Option D ("The web server uses a reverse DNS lookup of the client's IP address"): Incorrect, as reverse DNS lookup resolves an IP to a domain, which is irrelevant for the server determining the requested application.
The correct answer is A, aligning with the CAP syllabus under "Web Server Configuration" and "HTTP Protocol Security."References: SecOps Group CAP Documents - "HTTP Headers," "Virtual Hosting," and
"OWASP Web Security Testing Guide" sections.
NEW QUESTION # 39
You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?
- A. Requested changes
- B. Qualitative risk analysis
- C. Risk audits
- D. Quantitative risk analysis
Answer: A
NEW QUESTION # 40
You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou're your company.
You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?
- A. Risk mitigation
- B. Risk transference
- C. Risk acceptance
- D. Risk avoidance
Answer: B
Explanation:
Section: Volume A
NEW QUESTION # 41
......
Valid CAP Dumps for Helping Passing The SecOps Group Exam: https://www.trainingquiz.com/CAP-practice-quiz.html
Practice Exam CAP Realistic Dumps Verified Questions: https://drive.google.com/open?id=1K6vK5ft0u5ko2RChJ7tYsaoFTIhBBEhq