NEW QUESTION 17
Which of the following solutions are feasible when using the time series supply optimizer? Note: There are 3 correct Answers to this question.

  • A. Not respecting production capacity
  • B. Not-fully satisfied demands
  • C. Violation of minimum resource utilization
  • D. Not adhering to maximum transport values
  • E. Violation of minimum aggregated inventory values

Answer: B,C,E

 

NEW QUESTION 18
Which of the following key functions are supported by SAP IBP for sales and operations? Note: There are 2 correct Answers to this question.

  • A. Manual creation of feasible constrained plans
  • B. An advanced demand planning process
  • C. Finite resource planning
  • D. A basic demand planning process

Answer: C,D

 

NEW QUESTION 19
What does ABC/XYZ segmentation allow you to do? Note: There are 2 correct Answers to this question.

  • A. Analyze forecast accuracy by product class.
  • B. Identify inventory items that require closer attention.
  • C. Tailor your forecast strategy and inventory optimization to segment characteristics.
  • D. Assign more appropriate inventory algorithms to planning objects.

Answer: A,C

 

NEW QUESTION 20
What are some of the available ABC segmentation methods in IBP? Note: There are 2 correct Answers to this question.

  • A. By Number of Items (Sorted Values)
  • B. By Pareto Principle (Sorted and Calculated Values)
  • C. By Pareto Principle (Sorted and Cumulated %)
  • D. By Number of Items (Sorted Average)

Answer: A,B

 

NEW QUESTION 21
Which of the following can be used as inputs for inventory level optimization? Note: There are 2 correct Answers to this question.

  • A. Lead time variability
  • B. Lot sizes
  • C. Target inventory level
  • D. Reorder point

Answer: A,B

 

NEW QUESTION 22
Which of the following data can be tracked using a change-history-enabled key figure? Note: There are 3 correct Answers to this question.

  • A. Modified date
  • B. Key figure type
  • C. Scenario ID
  • D. Reason code
  • E. Attributes

Answer: A,D,E

 

NEW QUESTION 23
How can you check if key figure is editable or non-editable?

  • A. Using the Web-based Planning app when selecting key figures
  • B. Using the Edit View and then the Edit Planning View option
  • C. Using the Key Figure Calculations app
  • D. Using the Analytics Advanced app when selecting key figures

Answer: A

 

NEW QUESTION 24
You want to display and edit data in different units of measure (UOM). Which of the following must you consider before you use UOM? Note: There are 3 correct Answers to this question.

  • A. Units of measure are usually not time-dependent.
  • B. Unit of measure is an attribute of a master data type, such as Product.
  • C. Analytics provide the user with the option to select the target unit of measure.
  • D. Units of measure are usually not time-independent.
  • E. Conversion to the target unit of measure is handled by functionality of SAP IBP Excel UI

Answer: A,B,C

 

NEW QUESTION 25
Which SAP IBP planning operator can be run to delete planning objects in a certain version?

  • A. Purge Master Data
  • B. Purge Key Figure Data
  • C. Purge Key Figure Data Outside Planning Area Planning Horizon
  • D. Purge Non-Confirming Data

Answer: B

 

NEW QUESTION 26
What actions can be performed in the Advanced Dashboards application? Note: There are 3 correct Answers to this question.

  • A. Link two analytics charts.
  • B. Display all assigned analytics on a single UI.
  • C. Organize charts.
  • D. Add process templates.
  • E. Rename the charts.

Answer: B,C,D

 

NEW QUESTION 27
What are S&OP operator (optimizer) parameters associated with demand fair share?

  • A. Number of fair share segments. Maximum inventory. Additional tiering costs (default)
  • B. Number of fair share segments. Additional tiering costs (default). Number of fair share segments late delivery
  • C. Number of fair share segments. Maximum days of coverage. Number of fair share segments late delivery
  • D. Number of fair share segments. Additional tiering costs (default). Target inventory violation cost
  • E. You want to copy a custom planning area that was built during the SAP IBP implementation to model a separate process.

Answer: B

 

NEW QUESTION 28
Which header name displays are available in the Report Options menu of the SAP IBP Excel interface?Note:
There are 2 correct Answers to this question.

  • A. Business meaning, as defined in configuration
  • B. Changed member names that the user had created
  • C. Caption, as defined in configuration for the default name
  • D. Full unique name including the dimension and technical name

Answer: A,D

 

NEW QUESTION 29
Which of these conditions must be met to create a Local Member key figure?

  • A. A key figure is selected in the Key Figures tab in the Microsoft Excel add-in.
  • B. Activate Local Member Recognition is selected.
  • C. A key figure is created in the Planning Area app.
  • D. Use Excel Cell References in Report Editor is selected.

Answer: B

 

NEW QUESTION 30
What is a prerequisite for modeling outsourced manufacturers with production capacity?

  • A. Ensure that multiple modes of transportation are set up.
  • B. Model target inventory and stocks at the outsourced location.
  • C. Use production lead times and offsets to manage components at the outsourced location.
  • D. Model production costs for internal and external production resources to model priority.

Answer: D

 

NEW QUESTION 31
You are working with the inventory optimization process and you want to use a what-if analysis. What parameters are assessed by this analysis? Note: There are 2 correct Answers to this question.

  • A. Number of planning combinations
  • B. Changed variability
  • C. Capacity consumption
  • D. Service levels

Answer: B,D

 

NEW QUESTION 32
Which property of an attribute will allow it to be used as an attribute as a key figure?

  • A. Type INTEGER
  • B. Type DECIMAL
  • C. Type NAVCHAR
  • D. Type TIMESTAMP

Answer: B

 

NEW QUESTION 33
Which of the following stages can be modeled using scenarios from the S&OP planning cycle? Note:
There are 2 correct Answers to this question.

  • A. Data input review for inventory
  • B. Demand-supply balancing
  • C. Demand sensing stage
  • D. Demand review

Answer: B,D

 

NEW QUESTION 34
For which of the following application jobs can you enter planning filters as parameters? Note: There are
2 correct Answers to this question.

  • A. Purge Non-Conforming Data
  • B. Purge Key Figure Data
  • C. Create Time Periods for Time Profiles
  • D. Purge Master Data

Answer: B,D

 

NEW QUESTION 35
You have set up infinite S&OP heuristics for unconstrained planning. What must you do to model inputs as constraints? Note: There are 2 correct Answers to this question.

  • A. Create product substitutions.
  • B. Enter transportation lead times.
  • C. Model adjusted transport receipts.
  • D. Set minimum and maximum lot sizes.

Answer: B,C

 

NEW QUESTION 36
You have set up a planning area and data is available. You adjust the necessary time profile settings and run the consistency check. Which settings can you change and still run a successful consistency check?
Note: There are 2 correct Answers to this question.

  • A. Add a new time profile level to the time profile.
  • B. Change the past and future horizon of the levels in the time profile.
  • C. Change the description of the attributes in the time profile.
  • D. Remove an attribute assigned to the time profile level if the attribute is used in a planning level.

Answer: B,C

 

NEW QUESTION 37
Which of the following settings can you use in your supply planning background job triggered from Excel? Note: There are 2 correct Answers to this question.

  • A. Target currency
  • B. UOM to ID
  • C. Type of algorithm to use
  • D. Planning unit

Answer: B,C

 

NEW QUESTION 38
SAP is transitioning IBP customers to the new process of export/import. What are some of the features of this new process? Note: There are 2 correct Answers to this question.

  • A. You can create a collection of items and export it.
  • B. You can export from a planning area that is on a different release.
  • C. You can move a transported item from one collection to another.
  • D. You can choose to import only some of the items that were exported.

Answer: B,C

 

NEW QUESTION 39
You define fixing for a key figure. Which of the following functions are available for this key figure? Note:
There are 2 correct Answers to this question.

  • A. Fixing is possible for system editable key figures.
  • B. Fixing is possible for a certain quantity of a key figure value.
  • C. Fixing is possible for manually editable key figures.
  • D. Fixing is possible for a certain period, including all child values in the hierarchy.

Answer: C,D

 

NEW QUESTION 40
......


SAP C-IBP-2111 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Create and use key figures and attributes
  • Key Figures & Attributes
Topic 2
  • Display, create, copy, edit, check, and activate a planning area
  • General Configuration of a Planning Area
Topic 3
  • Planning Operators & Application Jobs
  • Use Planning Operators
Topic 4
  • Configure supply planning, run various solvers to generate planning results
  • Supply and Response

 

Free SAP Certified Application Associate C-IBP-2111 Exam Question: https://www.trainingquiz.com/C-IBP-2111-practice-quiz.html