NEW QUESTION # 13
Which statement applies to the DSDM process?
- A. Provides an approach that can be used for all projects without change
- B. Can be configured and calibrated to cater for light or strong governance
- C. DSDM projects can deliver the phases in the DSDM process in any order
- D. Does not require the elaboration of supporting products for complex projects
Answer: B
NEW QUESTION # 14
Which purpose relates to the instrumental Success Factors?
- A. Positions DSDM projects for a successful outcome
- B. Inform the development of the Terms of Reference
- C. Informs the development of the Business Case
- D. Underpins the prioritization of requirements
Answer: C
NEW QUESTION # 15
What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?
- A. Business Analyst
- B. Team Leader
- C. Technical Coordinator
- D. Business Visionary
Answer: D
NEW QUESTION # 16
During what phase should the strategy for Iterative Development be considered?
- A. Pre-Project
- B. Evolutionary Development
- C. Feasibility
- D. Foundations
Answer: D
NEW QUESTION # 17
Which statement about change is correct for DSDM?
- A. Project operate with a changing world
- B. Change is a symptom of an inability to define requirements properly
- C. Avoid change whenever possible
- D. Change is inevitable and males estimating very difficult
Answer: A
NEW QUESTION # 18
Which practice provides an interactive environment in which all key players can contribute to the outcome?
- A. Modelling
- B. Iterative Development
- C. Facilitied Wordshop
- D. Timeboxing
Answer: C
NEW QUESTION # 19
What role normally facilitates the Daily Stand.up?
- A. Technical Advisor
- B. Business Advisor
- C. Team Leader
- D. Project manager
Answer: C
NEW QUESTION # 20
Which responsibility relates to the role of the Business Ambassador?
- A. Provide the team with strategic direction.
- B. Provide day-to-day detail of the requirements during timeboxes
- C. Resolve business issues and make financial decisions
- D. Responsible for the Business Case and project budget.
Answer: D
NEW QUESTION # 21
Identify the missing word in the following sentence.
The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.
- A. Visionary
- B. director
- C. Champion
- D. Governor
Answer: A
NEW QUESTION # 22
During what phase should a baseline of the Evolving Solution be put into operational use?
- A. Foundations
- B. Post-Project
- C. Evolutionary Development
- D. Deployment
Answer: D
NEW QUESTION # 23
How does DSDM differ from most other Agile approaches?
- A. It focuses on the entire project lifecycle
- B. It focuses on the collaborative working of teams
- C. It focuses on the development of products
- D. It focuses on the delivery of products
Answer: A
NEW QUESTION # 24
Who is responsible for the application of Principle 8, Demonstrate Control?
- A. Collectively applied by the whole team
- B. Team Leader
- C. Project Manager
- D. The project-level roles
Answer: A
NEW QUESTION # 25
How is contingency typically managed in a DSDM project?
- A. Not needed in a DSDM project.
- B. Managed by varying time and cost
- C. Managed by varying the features to be delivered.
- D. Allowed adding a percentage to the high-level estimates.
Answer: C
NEW QUESTION # 26
What is the purpose of the Foundations Summary?
- A. To document how stakeholders will be engaged and standards that will be applied.
- B. To provide enough information to decide whether the project is likely to deliver return on investment
- C. To define the scope of the requirements that the project needs to address
- D. To define the tools, techniques, customer, practices and standards that will be applied
Answer: B
NEW QUESTION # 27
What DSDM product describes how the benefits have actually accrued following a period in live operation?
- A. Delivery Plan
- B. Prioritized Requirement List
- C. Benefits Assessment
- D. Project Review Report
Answer: C
NEW QUESTION # 28
When using the Iterative Development technique, which of the following should each cycle include?
1. Though
2. Action
3. Control
4. Conversation
- A. 2, 3, 4
- B. 1, 2, 3
- C. 1, 3, 4
- D. 1, 2, 4
Answer: C
NEW QUESTION # 29
What is the MoSCoW technical used for?
- A. As an opportunity to share information across the team and to do any day.to.day re-planning and reorganizing as necessary when issues occur.
- B. Understanding and managing priorities.
- C. Creating a visual representation of a problem or a solution.
- D. Ensuring a team-based approach through visual and verbal communication and collaboration.
Answer: B
NEW QUESTION # 30
Which of the following support the DSDM philosophy and principles?
- A. People, products, phase and plans
- B. Process, people, products and practices
- C. Phases, productivity, power and process
- D. Plans, projects, process and people
Answer: B
NEW QUESTION # 31
When should the quality of the evolving solution first be tesed?
- A. At the end of a Timebox
- B. As part of the iterative Development process
- C. At the end of a project.
- D. At the end of each increment
Answer: B