NEW QUESTION # 13
Which statement applies to the DSDM process?

  • A. Provides an approach that can be used for all projects without change
  • B. Can be configured and calibrated to cater for light or strong governance
  • C. DSDM projects can deliver the phases in the DSDM process in any order
  • D. Does not require the elaboration of supporting products for complex projects

Answer: B


NEW QUESTION # 14
Which purpose relates to the instrumental Success Factors?

  • A. Positions DSDM projects for a successful outcome
  • B. Inform the development of the Terms of Reference
  • C. Informs the development of the Business Case
  • D. Underpins the prioritization of requirements

Answer: C


NEW QUESTION # 15
What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?

  • A. Business Analyst
  • B. Team Leader
  • C. Technical Coordinator
  • D. Business Visionary

Answer: D


NEW QUESTION # 16
During what phase should the strategy for Iterative Development be considered?

  • A. Pre-Project
  • B. Evolutionary Development
  • C. Feasibility
  • D. Foundations

Answer: D


NEW QUESTION # 17
Which statement about change is correct for DSDM?

  • A. Project operate with a changing world
  • B. Change is a symptom of an inability to define requirements properly
  • C. Avoid change whenever possible
  • D. Change is inevitable and males estimating very difficult

Answer: A


NEW QUESTION # 18
Which practice provides an interactive environment in which all key players can contribute to the outcome?

  • A. Modelling
  • B. Iterative Development
  • C. Facilitied Wordshop
  • D. Timeboxing

Answer: C


NEW QUESTION # 19
What role normally facilitates the Daily Stand.up?

  • A. Technical Advisor
  • B. Business Advisor
  • C. Team Leader
  • D. Project manager

Answer: C


NEW QUESTION # 20
Which responsibility relates to the role of the Business Ambassador?

  • A. Provide the team with strategic direction.
  • B. Provide day-to-day detail of the requirements during timeboxes
  • C. Resolve business issues and make financial decisions
  • D. Responsible for the Business Case and project budget.

Answer: D


NEW QUESTION # 21
Identify the missing word in the following sentence.
The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.

  • A. Visionary
  • B. director
  • C. Champion
  • D. Governor

Answer: A


NEW QUESTION # 22
During what phase should a baseline of the Evolving Solution be put into operational use?

  • A. Foundations
  • B. Post-Project
  • C. Evolutionary Development
  • D. Deployment

Answer: D


NEW QUESTION # 23
How does DSDM differ from most other Agile approaches?

  • A. It focuses on the entire project lifecycle
  • B. It focuses on the collaborative working of teams
  • C. It focuses on the development of products
  • D. It focuses on the delivery of products

Answer: A


NEW QUESTION # 24
Who is responsible for the application of Principle 8, Demonstrate Control?

  • A. Collectively applied by the whole team
  • B. Team Leader
  • C. Project Manager
  • D. The project-level roles

Answer: A


NEW QUESTION # 25
How is contingency typically managed in a DSDM project?

  • A. Not needed in a DSDM project.
  • B. Managed by varying time and cost
  • C. Managed by varying the features to be delivered.
  • D. Allowed adding a percentage to the high-level estimates.

Answer: C


NEW QUESTION # 26
What is the purpose of the Foundations Summary?

  • A. To document how stakeholders will be engaged and standards that will be applied.
  • B. To provide enough information to decide whether the project is likely to deliver return on investment
  • C. To define the scope of the requirements that the project needs to address
  • D. To define the tools, techniques, customer, practices and standards that will be applied

Answer: B


NEW QUESTION # 27
What DSDM product describes how the benefits have actually accrued following a period in live operation?

  • A. Delivery Plan
  • B. Prioritized Requirement List
  • C. Benefits Assessment
  • D. Project Review Report

Answer: C


NEW QUESTION # 28
When using the Iterative Development technique, which of the following should each cycle include?
1. Though
2. Action
3. Control
4. Conversation

  • A. 2, 3, 4
  • B. 1, 2, 3
  • C. 1, 3, 4
  • D. 1, 2, 4

Answer: C


NEW QUESTION # 29
What is the MoSCoW technical used for?

  • A. As an opportunity to share information across the team and to do any day.to.day re-planning and reorganizing as necessary when issues occur.
  • B. Understanding and managing priorities.
  • C. Creating a visual representation of a problem or a solution.
  • D. Ensuring a team-based approach through visual and verbal communication and collaboration.

Answer: B


NEW QUESTION # 30
Which of the following support the DSDM philosophy and principles?

  • A. People, products, phase and plans
  • B. Process, people, products and practices
  • C. Phases, productivity, power and process
  • D. Plans, projects, process and people

Answer: B


NEW QUESTION # 31
When should the quality of the evolving solution first be tesed?

  • A. At the end of a Timebox
  • B. As part of the iterative Development process
  • C. At the end of a project.
  • D. At the end of each increment

Answer: B


NEW QUESTION # 32
......